Client

Desalination Power Plant

Scope

To inspect & assess existing Crane Supporting Wall & perform the required remedial works

Location

Power Generation Plant, Jebel Ali

Contractor

Perfection Frontier Contracting LLC

MONORAIL CRANE SUPPORTING WALL RESTORATION

An Overhead Crane of more than 20 ton of weight was resting on a 73 m long concrete wall, since many years in power generation area at Dubai Aluminum which severed the plant in lifting and moving of heavy loads for the operations. The existing wall had several defects and damages, which mainly includes horizontal cracks due to corrosion of internal reinforcement, external chloride penetrating the concrete surface causing concrete delamination.

PFC inspected & assessed the existing Crane Supporting Wall & performed the required remedial works to ensure its operational suitability for the  next 50 years. PFC carried out the visual inspections, conducted various Semi DT & NDT concrete tests for investigations. As per the remedial methodology formed, PFC repaired & restored the concrete wall which can now be last for another 50 years.

Global Leadership of PFC Group

OUR CLIENTILE