KLP 4&5 - Bld 9 - KIZAD Critical Warehouses Storage Faculties

The project was issued by Abu Dabhi Ports Authority in KIZAD to main contractor Trojan General Contracting who allocated the Steel Fabrication to Mabani Steel and PFC to Erect the 1,000 ton of steel and install 200,000 square feet of Sandwich Panels Roof and Walls Cladding.

The main challenge in this critical ware houses hand over was the tight time frame to deliver all statures to client, various trades were executed parallel at site which required very high level of day to day site coordination.

PFC engineering team was working under day to day modification upon site and client requirements to accommodate all new changes and adapt best engineering practice to avoid any time and materials wastage.