Power Generation Plant jebel Ali using Gas Turbine(GT) / Steam turbine(ST).
HV/LV cables for Switch gear room passes through underground basement built in the buildings were Deterioration found on internal faces of wall & floor with high corrosion potentials rate and chloride content in the form of chloride, hence lead to corrosion of rebar and relatively damaged the concrete.
PFC offered specialized services for refurbishing these damages on cable basement which may cause any power shutdown to plant.
PFC restored the floor using high strength free-flowing, non-shrink, cement based micro-concrete to repair all the delaminated and spalled concrete. The major constraints of this was to work in a confined space in hot weather condition and a high voltage zone which made this as a challenging project.